An audit measures your air before anyone sells you anything
A compressed air audit is a structured measurement of your compressed air system. It establishes how much air the plant uses, at what pressure and quality, when, and how much electricity it takes to produce it. It then identifies where air and energy are wasted, such as leaks, excess pressure, poor control and inappropriate uses, and ranks the fixes. A good audit gives you a measured baseline in kWh/m³, a demand profile, a pressure profile, a tagged leak list and costed recommendations. Without the baseline, no later saving can be verified.
This article explains what an audit covers, the levels of depth available, and what the report should contain. It is part of our industrial compressed air guide.
What a proper audit looks at
The international reference is ISO 11011:2013, which sets requirements for conducting and reporting a compressed air energy efficiency assessment. As the US Department of Energy’s compressed air sourcebook summarises it, the standard treats the system as three parts.
In practice, an audit covers each part as follows.
- Supply: compressor inventory, condition and control settings; package power; load and unload behaviour; unloaded power; room ventilation and intake temperature.
- Transmission: pressure drop across each dryer and filter; pressure dew point; drains and condensate handling; receiver size and position; piping layout and dead ends.
- Demand: which machines need which pressure and quality; leaks; open blowing and other inappropriate uses; off-production demand.
Three levels of depth
Not every plant needs the same depth. Guidance from the DOE and the Compressed Air Challenge describes three levels.
| Level | Typical duration (DOE/CAC) | What it involves | Best for |
|---|---|---|---|
| Walk-through evaluation | Half a day to 2 days | Visual review of supply, distribution and end uses; obvious problems; written findings | A first look, or a small single-compressor plant |
| System assessment | 2 to 5 days | Spot readings at key points; block diagram; pressure and demand profiles | Most plants deciding on improvements |
| Fully instrumented audit | 3 to 10 days on site | Data logging across the system over time; detailed baseline; supply and demand aligned | Large halls, major investment decisions, verified savings |
Data logging for the instrumented level usually runs for at least one full production week, so the record includes nights, weekends and changeovers.
What you should get from the report
The report is the product. If it does not contain measured data, you have bought an opinion. A useful audit report includes the items below.
What a good audit report contains
- A block diagram of the system: compressors, treatment, receivers, main piping
- A demand profile: flow over time across a full production week
- A pressure profile: pressure at the compressor, after treatment and at the far end of the system
- Power and energy: kW over time, annual kWh, and specific energy in kWh/m3
- Air quality: measured pressure dew point, and the ISO 8573-1 class each user needs
- Leak rate, plus a tagged leak list with location, size and priority
- Off-production demand, measured separately
- Ranked actions with estimated cost, energy effect and the assumptions behind each
- A measurement plan for verifying results after implementation
The ranking matters as much as the findings. The usual order is to remove waste first, through leak repair, lower pressure and switching off unneeded uses, then fix control, and only then consider new compressors. Buying capacity to feed leaks is the most expensive outcome.
If the report has no baseline, nothing that follows can be verified.
A baseline you can compare like with like
A baseline is only useful if the after-measurement can be compared with it fairly. Compressed air demand moves with production. A plant that runs more shifts after a project will use more air, whatever was improved.
So a good audit records what drives demand during the baseline period: production output, shifts, operating hours and, where relevant, outdoor temperature. Savings are then calculated as the change in energy after adjusting for those drivers, multiplied by the tariff agreed in advance. That is the difference between a verified saving and a before-and-after meter reading.
Agree three things before the audit starts:
- The boundary. Which compressors, dryers and other equipment are inside the measurement, and which are not.
- The normalisation. Which production figure, such as tonnes, pieces or machine hours, the energy will be adjusted to.
- The tariff. The electricity price used to turn kWh into money, so the result is not argued over later.
Questions to ask before you commission an audit
- Which level of audit is proposed, and why that level for this plant?
- What will be logged, at which points, and for how long?
- Which instruments are used, and are they calibrated?
- Will the leak rate be measured, and will leaks be tagged?
- Will pressure dew point be measured at the dryer outlet and at users?
- What does the report contain, and can we see a sample?
- How will results be verified after implementation?
Why measurement beats estimation
Most plants know their electricity bill but not what share the compressors take, or what a cubic metre of air costs. Nameplate power and running hours give a rough figure. Logged power and flow give a real one, and the two often differ.
The baseline also protects you. Savings are project-specific. We measure them against a baseline and verify them after implementation; we don’t promise a blanket percentage. A supplier who offers a fixed saving figure before measuring anything is guessing.
Ask how independent the advice is
The DOE sourcebook says assessments should maintain solution and product neutrality. That is a fair test for any auditor, including us. We are an authorised distributor of Ingersoll Rand and Sollant compressors, so you should expect us to show the measurement behind every recommendation. If the data says repair leaks, lower pressure and add a sequencer rather than buy a compressor, the report should say exactly that.
How the audit works in a Cambodian plant
A few local points are worth planning for:
- Moisture. Hot, humid intake air means a lot of condensate. Measuring pressure dew point and checking drains often explains corrosion, wet air at machines and dryer problems.
- Room temperature. Compressor room temperature is logged alongside power. Rooms that trap their own heat show up quickly in the data.
- Seasonal production. If output changes between seasons, the audit either covers a representative period or adjusts for it.
- Leak testing. A leak-rate test is best done when production is stopped, often on a Sunday or holiday, and is scheduled with you.
Leak findings often lead directly to a leak detection and repair programme. Our article on compressed air leaks explains how that works.
After the audit
The audit should end with a plan you can act on, in stages if needed. Some actions cost little, such as fixing leaks, adjusting setpoints and switching off unused branches. Others need engineering: re-piping, new control or new machines. Whatever you implement, repeat the same measurements afterwards. That is how a saving becomes a verified number rather than a claim.
You can get a first estimate of what your air costs today with our compressed air cost calculator. For the measured version, our compressed air audit follows the structure above, and our delivery process explains how findings turn into a project. Start by telling an engineer how many compressors you run and when your plant is in production.